HOME

SCHOOL INFORMATION

SCHOOL CALENDAR

ADMISSIONS

PRINCIPAL LETTER

PTO

SPORTS

ST. MICHAEL PARISH

 

CYBERCENTER

PHOTO GALLERIES

 
 

 

 

 

Building Our Community Of Faith Campaign

 

 

 

    

 

FAQs

  1. Where are we with the capital campaign? 
    How much money do we have?  How much do we need to get started building? 

    The campaign has stalled while negotiating with the Town of Cary on the traffic study requirements.  We expect to have the issues with the Town resolved shortly.  To date, we have approximately $2.3M in pledges, which includes $1.1M in actual donations and a $500k donation to the project by the parish.  To start construction, we need to have a total of approximately $3M in the bank.  This means we need another $1.4M in cash.  We still need to raise 50% of the total project cost, so fundraising will continue after construction begins.  Ideally, we would like to raise 100% of the total cost in donations so no mortgage is needed.

  2. How much is this project going to cost? 
    The total cost is estimated to be $9M, which includes construction costs, architectural fees, legal fees, impact fees, and traffic improvement adjustments.

  3. How many pledges have we received?  How many from school families vs. parish at large? 
    We are auditing the pledge cards to get an accurate count on total pledges, but the estimate at this time is approximately 750 total pledges, of which the school families have made approximately 180 (57% of total families). 

  4. Why haven’t we heard any updates since last year? 
    Many factors have slowed the campaign.  First, our co-chair who was driving the campaign became ill with cancer early in 2009 and passed away this summer.  Second, the Town of Cary has been hesitant to agree to our proposals to satisfy the traffic study requirements due to other potential projects in the High House – Cary Parkway corridor.  Third, we are just getting committees re-started to focus on specific tasks.  Finally, the economic downturn has had a negative impact on our volunteer base and our donation total, which has prevented us from making enough progress in the capital campaign to be noteworthy.

  5. Who is the contractor?  Were bids received to get the best price? 
    The Diocese and St. Michael’s have a longstanding relationship with Clancy & Theys.  They gave us their commitment to get the best pricing on materials and subcontractors possible while maintaining the quality that is present in all other buildings on our campus.  Their familiarity with our other projects makes them uniquely qualified to complete this project in the shortest time with the lowest total cost.

  6. Is expansion necessary?  Is there still a waiting list? 
    Over the past 2.5 years, our parish has assessed our growth and found that space limitations are a problem for both the parish and the school.  The master plan for the school originally included a gym and additional rooms, and this is the logical progression for the campus.  The waiting list is still present, even during the economic downturn.

  7. How will we pay the mortgage for the new building?  Will tuition increase? 
    The Diocese will loan the money needed to complete the project on a 15-year term loan.  We believe the incremental increase in tuition revenue through the addition of new students will be enough to pay for additional staff as well as the mortgage, without raising tuition.  The existing school mortgages are scheduled to be paid off over the next 5 years, freeing up even more revenue to cover school expenses.

  8. Have we considered modifying existing buildings instead? 
    Our architect studied an idea to reconfigure the Trinity Center and Archangel Center to allow the Trinity Center to become a middle school and the Archangel Center to become the ECC.  This plan also included modifying the Parish Center to become a full-size gymnasium.  The result of this study was that such a project would be more costly and take longer due to the costs to upfit both the Trinity Center and Archangel Center buildings to handle these new roles.  It would also consume the existing ECC playground without creating the dining hall and stage facilities that we desperately need.  In the end, the idea was rejected and focus returned to the original plan.

  9. Is this the last capital campaign we can expect? 
    We can’t say with certainty that we will never need to have another capital campaign, but once the school building is complete, expansion on our campus will be complete.  The parish will continue to face financial challenges, such as debt reduction, capital improvements, and other unforeseen expenses, so a future campaign is always a possibility.

  10. What happens when the church’s debt is paid off?  Will that money be applied to the school debt? 
    The Church’s financial status continues to be monitored closely to ensure that parish funds are managed properly.  As the mortgages are paid off, the Finance Council will re-assess the best use of our funds and apply them where they have the most benefit for the parish.

  11. Why don’t we set up an endowment instead of expanding the school? 
    An endowment would be an excellent addition to our school, but it does not fill the need to add space and seats to provide Catholic education to more students.  Once the building project is complete, an endowment to make tuition more affordable would be a worthwhile follow-on project.

  12. Is the church able to take on more debt during this economic downturn? 
    That is ultimately up to the Diocese to determine, but we feel confident that our plan is convincing.  Debt payment will be secured by the increased tuition revenue, and the debt payment schedule for the parish debt makes us confident that we will be able to absorb other unforeseen expenses while servicing this additional debt.

  13. Best case, when can construction start? 
    Based on the Town of Cary approval process, the soonest we could start construction would be around March 1 of 2010.  This assumes we have the necessary funds to get started as well as Diocesan approval, too.

  14. How long will construction take? 
    Estimates from the builder predict 12 months for this project.  Clancy & Theys is making a new project plan with an actual schedule that will also include potential time savings on the total project schedule.

  15. During construction, how much disruption will the students experience? 
    Classrooms have been reassigned this year to meet codes that require children below a certain grade level to have direct access to a ground floor exit.  No further classroom changes are required.  Construction traffic will be routed through the entrance to the Archangel Center along a narrow road around the edge of the fields to the rear of the property.  All construction activity will be fenced off away from the children.  Normal construction noise will be unavoidable, but the builder has assured us that they would do everything they can to complete major structural construction in a timely manner.

  16. What happens to the sports field during construction? 
    A temporary access road will be added to the perimeter of the fields connecting the parking lot of the Archangel Center to the construction zone.  This road will be fenced off from the rest of the field so activities can continue during construction.  The fields may need to be reconfigured in some manner during this project.  Clancy & Theys has assured us that any temporary modifications to the field will be repaired at the completion of the project and the fields will be returned to the state they are in today.

  17. What does Cary require us to do based on the traffic study? 
    The Town Council has approved our proposals to satisfy our adequate public facilities requirements.  This includes building a right turn lane into our eastern-most parking lot, granting the right of way along High House Road for future widening, and making a one-time payment to the Town to cover our share of the expense for the Cary Parkway-High House Road intersection improvements and an eventual traffic signal in front of the church and Bond Park.  This is a major hurdle that could have prevented us from doing the project at all had they decided to put the burden of all road improvements to High House Road on St. Michael’s.

  18. What do we do if we open another class per grade and don’t have enough students to fill them? 
    The plan for expansion is to limit class sizes to 25 (75 students per grade).  This means we will add approximately18-20 students per grade.  If we find that there are not enough stewardship families to fill the open slots, we will open enrollment to other families in the community.

  19. Why not just build a gym? 
    Building the gym would block future construction of the other wing that would house the cafeteria and other classrooms.  Furthermore, building a gym alone does not satisfy our need for space for faith formation, adult education, and to reduce our school waiting list.
     

  20. It seems like the school will be the only group to benefit from this project.  Why should people not affiliated with the school donate? 
    The school building is used by the entire parish after school hours and on weekends.  The additional space, gymnasium, cafeteria, and chapel will benefit the entire community – not just the school.  The fact that school tuition funds the building entirely makes it even more important that the parish community support this project.

  21. Will the new facilities change any other services currently provided, such as the masses at Green Hope and the Parish Center? 
    These masses currently serve a specific need that would not be relieved adding a gymnasium, thus no changes are planned to the existing mass schedule.

  22. What will happen to the playground during and after construction? 
    During construction, the playground will be dismantled.  Younger children will be able to use the playground next to the parish center, while older children will have recess in the parking area near the school as they do now.  The playground will then be reassembled closer to the sports fields once construction is complete.
     

  23. How can we keep up to date on the progress of this project? 
    A communication committee has been formed with Frank Graff as the chairman.  We are planning to update the parish website, include updates in the weekly principal’s letter, create a display in the gathering space of the church, and insert bulletin updates on a weekly basis throughout the project.  We are also investigating the showing of a modified campaign video in the church to re-start fundraising in the near future.

  24. How will construction and the new building addition affect the carpool system? 
    The carpool system we currently use may need to be adjusted to handle additional vehicles – especially during dismissal carpool.  We have reviewed our system with a traffic engineering consultant and have been assured that we have enough parking lot space to effectively process the additional vehicles without any delays. 

  25. Will the new construction have any affect on the Weatherstone community? 
    All access to the campus will be through existing entrances, including access for construction vehicles.  The path between the campus and the Weatherstone community will remain unchanged. 

 

 

 

HOME

SCHOOL INFORMATION

SCHOOL CALENDAR

ADMISSIONS

PRINCIPAL LETTER

PTO

SPORTS

ST. MICHAEL PARISH

 

CYBERCENTER

PHOTO GALLERIES